The Washington Street Hill Is Being Rebuilt as Mission Hills' Walk to the Trolley

Most people call the construction on the Washington Street hill "the bike lane." SANDAG's plan covers more than that. It adds a walking path along the whole south side of Washington Street from India Street to University Avenue, a new bus island near India, high-visibility crosswalks, curb extensions and traffic signals. The bike lanes are part of the same package. Put together, the project changes how Mission Hills meets the Washington Street Trolley Station at the bottom of the hill. That bottom end is also where the work has been hardest to live with this fall.

Start at India Street, Because the Project Does

The official name is the Washington Street and Mission Valley Complete Streets project. It used to be called the Washington Street and Mission Valley Bikeway, and SANDAG says it changed the name "to more accurately reflect the work that we are doing." It is the third of four segments in the larger Uptown Complete Streets program.

Look at the Washington Street pieces one by one and most of them sit at the India Street end of the hill:

  • Separated bike facilities and shared bike-and-car lanes from the Washington Street Trolley Station to University Avenue, which SANDAG describes as "connecting the Middletown and Mission Hills neighborhoods"
  • A walking path on the south side of Washington Street from India Street to University Avenue
  • A bus island on the north side of Washington Street near India Street
  • Separated bike facilities on San Diego Avenue from Washington Street to Pringle Street, then buffered bike lanes on San Diego Avenue from Pringle to Noell Street

SANDAG manages construction. When the work is done, the City of San Diego will own and operate the bikeway.

The Bus Stops Moved First

Bus riders felt the India Street focus before anyone else. MTS Route 10, which runs from Old Town to University/College, has had both of its Washington Street and India Street stops closed since early spring. Both closures run through the end of the year.

Direction Closed stop Closure window Where MTS directs riders
Eastbound Washington St & India St, #13353 March 9 to Dec. 31, 2026 Washington & Pacific Highway, #13351
Westbound Washington St & India St, #13356 March 1 to Dec. 31, 2026 Washington St & Trolley Tracks, #99373

On the MTS Alerts & Detours page, both notices were last updated Sept. 14, 2026. MTS lists the westbound closure as part of the "Uptown Bikeways Project," the program's older name. The project's planned bus island is at the same corner, on the north side of Washington near India.

Where the Path and the Bike Lanes Lead

Once it's finished, the south-side walking path will run the length of the hill, from India Street up to University Avenue. That gives Mission Hills a continuous walking route from the University Avenue end of the neighborhood down to the trolley and bus connections at the bottom.

The bike side reaches further. On the Mission Valley half of the project, SANDAG lists these pieces:

  1. Shared lane markings and wayfinding signs on Third Avenue from Washington Street to Walnut Avenue, and on Walnut from Third to Fifth Avenue, connecting to the Fourth & Fifth Avenue Bikeways
  2. A contra-flow bike lane on Third Avenue from Washington Street to Lewis Street, and on Lewis Street from Bachman Place to Third Avenue
  3. Buffered bike lanes on Bachman Place from Lewis Street down to Hotel Circle South
  4. Separated bike facilities on Hotel Circle South, Camino De La Reina and Avenida Del Rio from Bachman Place to Riverwalk Drive, connecting Uptown to the San Diego River Trail
  5. A new sidewalk with room for an enhanced bus stop at Hotel Circle South and Bachman Place

The whole thing adds up to a 3.3-mile bikeway. The Fourth & Fifth Avenue segment it connects to is already in use. SANDAG lists that segment as complete and says it opened to the public in February 2022. When the Washington Street work wraps up, someone starting at the Washington Street Trolley Station could follow marked routes up through Mission Hills toward Hillcrest's avenue bikeways, or down Bachman Place toward the river trail.

What the Work Looks Like This Fall

The finished street is still ahead. Right now the hill is a construction zone, and this fall has been rough on drivers. On Sept. 20, 2026, NBC 7 San Diego reported that traffic on West Washington Street near Old Town had been cut to a single lane while crews built the new bike path. A driver NBC 7 interviewed said a trip of less than a mile took more than 15 minutes when she missed the light cycle. She also told the station she had noticed street parking disappearing where bike infrastructure is going in. The same report put this project in a bigger picture: seven bikeway projects are underway across San Diego, and together they will add more than 21 miles to the city's bike network.

Crews also worked at night. SANDAG's construction notice, updated Oct. 8, 2026, moved overnight work at Hancock Street and Washington Street to the nights of Oct. 12 and Oct. 15, from 9 p.m. to 5 a.m.

Neighborhood frustration has made the local paper. In an Oct. 7 commentary in the Presidio Sentinel, publisher Patty Ducey-Brooks wrote up her review of a month of Nextdoor comments from people who use Washington Street regularly. Her piece says delays of up to 30 minutes could push traffic onto nearby residential streets. One comment she quoted focused on the corner where the project starts:

"I think the intersection design at India and Washington requires a 2nd look."

That's the same corner as the closed Route 10 stops and the future bus island. Whether people are driving, waiting for a bus or picturing the finished design, their attention keeps landing on India Street.

Why It's Arriving Now

To a lot of people this construction seems to have shown up out of nowhere. The planning started more than a decade ago. SANDAG's own timeline shows how long the project spent on paper before crews broke ground:

  1. 2012 to 2014, planning. SANDAG worked with a community advisory group that met four times at key decision points on the route.
  2. 2014 to 2016, engineering and environmental clearance. On July 22, 2016, the SANDAG Board of Directors approved a California Environmental Quality Act exemption for all four Uptown segments.
  3. 2016 to 2024, final design. SANDAG describes this phase as fine-tuning aesthetics and design elements with the community and partners.
  4. 2025 to 2027, construction. Preliminary construction began in fall 2025.

In 2021 the Mission Hills BID posted a grant announcement for the Washington Street and Bachman Place bikeways. At that point design was underway, and the post said construction could start as soon as late 2022. The real start came about three years later. SANDAG's project page still gives the construction window as 2025 to 2027. NBC 7's September report said SANDAG expects the project to be finished next year.

The neighborhood's business group has been keeping an eye on it. At the BID's June 17, 2026 meeting, after the session reconvened as the Mission Hills Parking Advisory Committee, SANDAG's project information was shared, including the bike lane and the bus island. The "W. Washington Street SANDAG project" came up again as an information item in the Parking Advisory Committee section of the Sept. 16 agenda.

Getting Updates Before You Head Down the Hill

The night-work schedule has already shifted once this fall, so the SANDAG project page is the place to look for current notices. It also has an email sign-up for the Washington Street and Mission Valley project. SANDAG takes questions at [email protected] or 833.899.2453. If you ride Route 10, check the MTS alerts page through Dec. 31, the last day of both posted stop closures.

When the Washington Street hill reopens with a walking path from India to University and a bus island at the bottom, the walk from your front door to the trolley could look different than it does today. If you'd like to know how changes like this factor into what your Mission Hills home is worth, The Dream Homes Team can walk you through it. Request a Free Home Valuation and we'll start with your street.